[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123442":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123442,791,1,"单选题","砌块的吊装一般按施工段依次进行，一般以一个或两个单元为一个施工段，进行分段流水施工，其次序为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先外后内，先远后近，先上后下",false,{"key":16,"text":17,"correct":14},"B","先外后内，先近后远，先下后上",{"key":19,"text":20,"correct":14},"C","先内后外，先远后近，先下后上",{"key":22,"text":23,"correct":24},"D","先外后内，先远后近，先下后上",true,"P47-52 砌块的吊装一般按施工段依次进行，一般以一个或两个单元为一个施工段，进行分段流水施工。其次序为先外后内，先远后近，先下后上，在相邻施工段之间阳阶梯形斜槎。砌筑时应从转角处或定位砌块处开始，内外墙同时砌筑，错缝搭砌，横平竖直，表面清洁，按照砌块排列图进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]