[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123401,791,1,"单选题","地下连续墙的施工步骤中，次序颠倒的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","修筑导墙-分段成槽",false,{"key":16,"text":17,"correct":18},"B","浇筑混凝土-泥浆护壁",true,{"key":20,"text":21,"correct":14},"C","泥浆护壁-浇筑混凝土",{"key":23,"text":24,"correct":14},"D","浇筑混凝土-拔接头管","P55-58 在挖基槽前先作保护基槽上口的导墙，用泥浆护壁，按设计的墙宽与深分段挖槽，放置钢筋骨架，用导管灌注混凝土置换出护壁泥浆，形成一段钢筋混凝土墙。逐段连续施工成为连续墙。施工主要工艺为导墙、泥浆护壁、成槽施工、水下灌注混凝土、墙段接头处理等。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]