[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123358,791,1,"单选题","关于矿业工程施工测量实施的原则，正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从整体到局部、先控制后细部、由低级到高级",false,{"key":16,"text":17,"correct":14},"B","从局部到整体、先细部后控制、由低级到高级",{"key":19,"text":20,"correct":21},"C","从整体到局部、先控制后细部、由高级到低级",true,{"key":23,"text":24,"correct":14},"D","从局部到整体、先细部后控制、由高级到低级","P28-30 1.施工测量工作一般应遵循以下原则:（1）程序上符合由整体到局部的要求>;（2）实施的步骤是“先控制后细部”（3）精度上要求由高级到低级。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]