[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123357,791,1,"单选题","为保证各种建筑物、管线等位置能满足设计要求以及有利于分期分批施工，施工测量通常遵循（ ）原则。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先整体后局部",true,{"key":16,"text":17,"correct":18},"B","先局部后整体",false,{"key":20,"text":21,"correct":18},"C","先施工的先不测",{"key":23,"text":24,"correct":18},"D","整体、局部测量同时进行","P28-30 1.施工测量工作一般应遵循以下原则:（1）程序上符合由整体到局部的要求>;（2）实施的步骤是“先控制后细部”（3）精度上要求由高级到低级。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]