[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123341":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123341,791,1,"单选题","贯通测量最后一次标定贯通方向时，其未掘巷道长度应满足（ ）的要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不得小于50m",true,{"key":16,"text":17,"correct":18},"B","不得大于50m",false,{"key":20,"text":21,"correct":18},"C","不得大于20m",{"key":23,"text":24,"correct":18},"D","不得小于20m","P4-7 贯通测量至少应独立进行两次，取平均值作为最终值，最后一次标定贯通方向时，未掘的巷道长度不得小于50m",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]