[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123250,791,1,"单选题","关于近井点和井口高程基点的建立要求，以下说法错误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","近井点和井口高程基点应尽可能设在便于观测、保存的地方，不应受到采动影响",false,{"key":16,"text":17,"correct":14},"B","近井点至井筒连测导线边数不宜超过3 条；对多井筒的矿井地面近井点，应统一布置，尽可能使邻近井筒的近井点构成测量网的一条边线，或间隔的边数最少",{"key":19,"text":20,"correct":21},"C","水准基点不可少于3 个，合适的情况下，近井点也可作为水准基点",true,{"key":23,"text":24,"correct":14},"D","近井点和水准基点应埋设在结构坚固、稳定的井口附近建筑物上或井筒附近的地面上","水准基点不可少于2 个，合适的情况下，近井点也可作为水准基点。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]