[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123215,791,1,"单选题","关于《建筑基坑支护技术规程》中的地基设计的相关内容，以下说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按地基变形设计或应作变形验算且需进行地基处理的建筑物或构筑物，应对处理后的地基进行变形验算",false,{"key":16,"text":17,"correct":14},"B","受较大水平荷载或位于斜坡上的建筑物及构筑物，当建造在处理后的地基上时，应进行地基稳定性验算",{"key":19,"text":20,"correct":14},"C","强夯置换法在设计前必须通过现场试验确定其适用性和处理效果",{"key":22,"text":23,"correct":24},"D","水泥搅拌法用于处理泥炭土、有机质土、塑性指数大于25的黏土、地下水具有腐蚀性时以及无工程经验的地区，必须通过现场试验确定其适用性",true,"水泥搅拌法用于处理泥炭土、有机质土、塑性指数大于25的黏土、地下水具有腐蚀性时以及无工程经验的地区，必须通过现场试验确定其适用性。@jin",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]