[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123184,791,1,"单选题","矿山工程的（）必须和主体工程同时设计、同时施工、同时投人生产和使用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","生产设施",false,{"key":16,"text":17,"correct":14},"B","提升设施",{"key":19,"text":20,"correct":21},"C","安全设施",true,{"key":23,"text":24,"correct":14},"D","防尘设施","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]