[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123155,791,1,"单选题","与井筒相毗连的各种硐室(马头门、装载硐室等)在一般情况下应与井筒施工（）， 装载硐室的安装应在井筒永久装备施工之前进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","顺序进行",false,{"key":16,"text":17,"correct":14},"B","交替进行",{"key":19,"text":20,"correct":21},"C","同时进行",true,{"key":23,"text":24,"correct":14},"D","分别进行","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]