[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123152,791,1,"单选题","矿业工程项目施工总进度安排时，一般情况下（）是构成矿井工程项目关键路 线的关键工程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","井架安装",false,{"key":16,"text":17,"correct":14},"B","绞车安装",{"key":19,"text":20,"correct":21},"C","井筒施工",true,{"key":23,"text":24,"correct":14},"D","井筒装备","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]