[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123150,791,1,"单选题","矿业工程项目在进行施工现场准备时，关于需要完成的任务，说法不正确的 是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","做好施工场地的控制网测量施测工作",false,{"key":16,"text":17,"correct":14},"B","平整工业广场，清除障碍物",{"key":19,"text":20,"correct":21},"C","完成“三通一平”工作",true,{"key":23,"text":24,"correct":14},"D","提出设备、机具、材料进场计划，并组织施工机具进场、组装和保养工作","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]