[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123148,791,1,"单选题","矿业工程施工准备工作内容比较复杂，其中技术准备工作的内容一般不考虑( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","掌握施工要求与检査施工条件",false,{"key":16,"text":17,"correct":14},"B","会审施工图纸",{"key":19,"text":20,"correct":21},"C","完成“四通一平”工作",true,{"key":23,"text":24,"correct":14},"D","编制施工组织设计","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]