[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123143,791,1,"单选题","矿业工程项目开工前的准备阶段，为满足招标工作的需要，由（ ）编制矿井施 工组织设计，其内容主要是着重于大的施工方案，及总工期总投资概算的安排，一般在大 规模开工前6个月完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","施工单位",{"key":23,"text":24,"correct":14},"D","监理单位","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]