[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123140,791,1,"单选题","某矿建公司通过招投标方式承担立井井筒的施工任务，工期为18个月。为了在 18个月内完成施工任务，该矿建公司应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","增加大型施工设备",false,{"key":16,"text":17,"correct":14},"B","大量增加工作面的施工人员",{"key":19,"text":20,"correct":21},"C","狠抓关键工程的施工",true,{"key":23,"text":24,"correct":14},"D","狠抓所有工程的施工","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]