[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123139,791,1,"单选题","某矿建公司通过招投标方式承担了立井井筒的施工任务，因工期紧，建设单位 在进场道路尚未全面完成的情况下即要求该矿建公司进场施工。该矿建公司为了进场 方便，在建设单位的指令下支出30万元完善了进场道路，矿建公司支出的30万元应由 ( )承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","矿建公司",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","当地政府",{"key":23,"text":24,"correct":14},"D","矿建公司和建设单位共同","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]