[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123129,791,1,"单选题","根据是否具有独立生产功能和独立施工条件，以及预算和结算的条件的不同，矿 业工程项目一般划分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单项工程、单位工程和分项、分部工程",true,{"key":16,"text":17,"correct":18},"B","矿井建设工程与矿山开采工程",false,{"key":20,"text":21,"correct":18},"C","地面工程与地下工程",{"key":23,"text":24,"correct":18},"D","矿建工程、土建工程和机电安装工程","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]