[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123085":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123085,791,1,"单选题","一承包商承揽了一井筒的施工任务，施工准备由承包商负责，业主协助，施工中 发生的（）事件承包商可以向业主进行索赔。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","井口场地未进行平整而无法竖立井架",false,{"key":16,"text":17,"correct":14},"B","施工人员技术水平低而延误进度",{"key":19,"text":20,"correct":14},"C","施工设备没有及时进场而延误开工",{"key":22,"text":23,"correct":24},"D","施工图纸不能及时提供而延误施工",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]