[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123082,791,1,"单选题","矿业工程施工中，关于索赔与变更的不正确表述是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","索赔和变更都处理原合同上没有的内容或没有正常执行的内容",false,{"key":16,"text":17,"correct":14},"B","变更通常是在施工前或施工过程中，索赔通常是在施工过程甚至更晚的时候",{"key":19,"text":20,"correct":14},"C","变更可能引起索赔，但不是一定引起索赔",{"key":22,"text":23,"correct":24},"D","索赔和变更总是同时发生和存在的",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]