[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123050,791,1,"单选题","下列关于矿业工程量变更计算的规定表述错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量清单漏项或由于设计变更引起的新的工程量清单项目，其相应综合单 价由承包方提出，经发包方确认后作为结算的依据",false,{"key":16,"text":17,"correct":14},"B","由于设计变更引起工程量增减部分，属于合同约定幅度以内的，应执行原有的 综合单价",{"key":19,"text":20,"correct":14},"C","增减工程量属于合同约定幅度以外的，其综合单价由承包人提出，经发包人确 认以后作为结算的依据",{"key":22,"text":23,"correct":24},"D","由于工程量的变更，且实际发生了规定以外的费用损失，承包人不可提出索赔 要求",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]