[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123049,791,1,"单选题","不属于矿业工程项目工程量变更的条件的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因设计局部修改",false,{"key":16,"text":17,"correct":14},"B","因工程施工中客观条件变化而修改施工图设计",{"key":19,"text":20,"correct":21},"C","超过本单位工程预备费率部分的“三材”",true,{"key":23,"text":24,"correct":14},"D","因材料代用所增加的费用","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]