[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123025,791,1,"单选题","井筒竣工验收时要求普通法施工的井筒建成后总漏水量不得大于（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3m3\u002Fh",false,{"key":16,"text":17,"correct":14},"B","5m3\u002Fh",{"key":19,"text":20,"correct":21},"C","6m3\u002Fh",true,{"key":23,"text":24,"correct":14},"D","8m3\u002Fh","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]