[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123015,791,1,"单选题","地下连续墙施工前宜进行（）试验，确定施工工艺流程，选择操作技术参数。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","泥浆配合比",false,{"key":16,"text":17,"correct":14},"B","混凝土配合比",{"key":19,"text":20,"correct":14},"C","c.槽壁稳定性",{"key":22,"text":23,"correct":24},"D","墙槽成槽",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]