[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1122991,791,1,"单选题","关于利用横道图计划表示矿业工程项目的施工进度的缺点，以下说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不能明确地反映出各项工作之间错综复杂的相互关系。",false,{"key":16,"text":17,"correct":18},"B","形象、直观，且易于编制和理解，因而长期以来应用比较普及",true,{"key":20,"text":21,"correct":14},"C","不能反映出工作所具有的机动时间",{"key":23,"text":24,"correct":14},"D","不能反映工程费用与工期之间的关系","选项B 所描述的内容，是利用横道图计划表示矿业工程项目的施工进度的主要优点。 利用横道图计划表示矿业工程项目的施工进度的缺点，还包括： 1不能明确地反映出影响工期的关键工作和关键线路，也就无法反映出整个工程项。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]