[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1122990,791,1,"单选题","关于进度控制的一般性措施，以下说法错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","突出关键路线，坚持抓关键路线。",false,{"key":16,"text":17,"correct":14},"B","加强生产要素配置管理。配置生产要素是指对劳动力、资金、材料、设备等进行存量、流量、流向分布的调查、汇总、分析、预测和控制",{"key":19,"text":20,"correct":14},"C","严格控制工序，掌握现场施工实际情况，为计划实施的检査、分析、调整、总结提供原始资料",{"key":22,"text":23,"correct":24},"D","征得业主的同意后，缩小工程的范围，包括减少工作量或删去一些工作包(或分项工程)",true,"选项D所描述的内容，是进度拖延的事后控制措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]