[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122988":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},1122988,791,1,"单选题","某矿施工网络图见图，其中B工作的机动时间为（ ）天。",[11,15,19],{"key":12,"text":13,"correct":14},"A","10",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","2","",{"id":6,"name":24,"category":25,"favorite":26},"二建矿业工程实务","建筑工程",0]