[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1122986,791,1,"单选题","矿业工程进度控制必须要优选施工方案，下列优选施工方案的具体措施不正确的 是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","根据实际情况，综合分析、全面衡量，缩短井巷工程关键线路的工程量",false,{"key":16,"text":17,"correct":14},"B","在制定各单位工程施工技术方案时，必须充分考虑自然条件",{"key":19,"text":20,"correct":21},"C","井巷工程关键路线贯通掘进，以主、副井方向开拓为主，风井为辅",true,{"key":23,"text":24,"correct":14},"D","采用的施工工艺、施工装备，要进行方案对比","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]