[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1122985,791,1,"单选题","矿山工程进度拖延的事后控制措施最关键的是（)。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析进度拖延的原因",true,{"key":16,"text":17,"correct":18},"B","投人更多资源加速施工",false,{"key":20,"text":21,"correct":18},"C","调整施工合同",{"key":23,"text":24,"correct":18},"D","修改设计","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]