[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1122983,791,1,"单选题","矿山工程项目进度控制由于影响因素多，控制技术复杂，因此必须认真进行分析 研究和规划，具体表现在（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","矿山工程项目是由矿建、土建和机电安装工程项目构成，在控制上具有相对 独立性，有利于实施进度控制",false,{"key":16,"text":17,"correct":18},"B","矿山工程项目由多系统组成，这些系统在施工过程中相互关联，相互影响，甚 至会制约工程的实际进度",true,{"key":20,"text":21,"correct":14},"C","矿山工程项目涉及较多的大型专用设备安装，实施进度控制将对矿山工程投资 的时间效益产生不利的影响",{"key":23,"text":24,"correct":14},"D","矿山工程施工条件十分复杂，需要采用科学的方法来进行进度控制并不断调整 工期，争取早日发挥经济效益","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]