[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1122982,791,1,"单选题","当关键工作的实际进度较计划进度落后时，调整的目标就是采取措施将耽误的时 间补回来，保证项目按期完成。调整的方法主要是缩短后续关键工作的持续时间，通常可( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","改变某些工作的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","增加某些工作的工作内容",false,{"key":20,"text":21,"correct":18},"C","减少某些工作的计划费用",{"key":23,"text":24,"correct":18},"D","改变某些工作的资源消耗","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]