[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1122979,791,1,"单选题","矿业工程项目矿、土、安三类工程的综合平衡，是决定整个矿山工程项目工期的 关键。依照矿山工程的特点，通常根据（）进度安排来布置各工作的施工顺序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","矿建工程",true,{"key":16,"text":17,"correct":18},"B","土建工程",false,{"key":20,"text":21,"correct":18},"C","安装工程",{"key":23,"text":24,"correct":18},"D","机电工程","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]