[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1122975,791,1,"单选题","矿业工程施工进度计划编制时，网络计划工作的重点是确定（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方案",false,{"key":16,"text":17,"correct":14},"B","施工方法",{"key":19,"text":20,"correct":14},"C","施工技术",{"key":22,"text":23,"correct":24},"D","施工顺序",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]