[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1122974,791,1,"单选题","矿井施工准备工期与矿井竣工工期之和构成矿井建设的总工期，矿井建设的总工 期一般可依据（）来进行推算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键生产系统的施工工期",false,{"key":16,"text":17,"correct":14},"B","全部生产系统的安装工期",{"key":19,"text":20,"correct":21},"C","矿井建设的关键线路工期",true,{"key":23,"text":24,"correct":14},"D","全部土建工程的施工工期","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]