[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122957":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1122957,791,1,"单选题","巷道施工机械化作业线设备的配套，应保证各工序所使用的机械设备在生产能力 上的匹配合理，下列配套方案不合理的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","多台气腿式凿岩机、耙斗式装载机、浮放道岔调车、矿车及电机车运输",false,{"key":16,"text":17,"correct":14},"B","多台气腿式凿岩机、蟹爪式装载机、梭式矿车及电机车运输",{"key":19,"text":20,"correct":14},"C","凿岩台车、铲斗侧卸式装载机、胶带转载机、矿车及电机车运输",{"key":22,"text":23,"correct":24},"D","钻装机、铲斗侧卸式装载机、胶带转载机、矿车及电机车运输",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]