[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1122950,791,1,"单选题","巷道掘进装岩过程中，工作面调车装载机的工时利用率接近100%的调车方法是( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","利用转载设备进行调车",true,{"key":16,"text":17,"correct":18},"B","活动错车场调车法",false,{"key":20,"text":21,"correct":18},"C","固定错车场调车法",{"key":23,"text":24,"correct":18},"D","浮放错车场调车法","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]