[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1122921,791,1,"单选题","立井井筒掘砌单行作业中，确定井筒掘进段高的因素是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","井筒深度、井壁结构、施工技术",false,{"key":16,"text":17,"correct":14},"B","井筒大小、支护结构、施工要求",{"key":19,"text":20,"correct":14},"C","井筒地质条件、井筒直径、施工水平",{"key":22,"text":23,"correct":24},"D","井筒穿过岩层的性质、涌水量大小、施工速度要求",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]