[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1122874,791,1,"单选题","关于SMW定位、钻孔施工，以下说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在开挖的工作沟槽两侧铺设导向定位型钢或定位辅助线，按设计要求在导向定位型钢或定位辅助线上做出钻孔位置和H 型钢的插入位置。根据确定的位置严格将钻机桩架移动就位。",false,{"key":16,"text":17,"correct":18},"B","开钻前应用水平尺将平台调平，并调直机架，确保机架垂直度不小于1% 。并在成孔、提升过程中经常检査平台水平度和机架垂直度，确保成桩垂直度不大于3%",true,{"key":20,"text":21,"correct":14},"C","为控制钻管下钻深度达标，利用钻管和桩架相对错位原理，在钻管上划出钻孔深度的标尺线，严格控制下钻、提升的速度和深度",{"key":23,"text":24,"correct":14},"D","下钻、提升速度应与注浆泵的泵量相适应，同时下钻速度不大于100cm\u002Fmin，提升速度不大于180c m \u002F m i n并至少复拌一次以上","开钻前应用水平尺将平台调平，并调直机架，确保机架垂直度不小于1% 。并在成孔、提升过程中经常检査平台水平度和机架垂直度，确保成桩垂直度不大于1%。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]