[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1122860,791,1,"单选题","地下连续墙施工各工序先后顺序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","导墙—分段成槽—泥浆护壁—浇筑混凝土",true,{"key":16,"text":17,"correct":18},"B","导墙—分段成槽—掉放接头管—浇筑混凝土",false,{"key":20,"text":21,"correct":18},"C","导墙—分段挖土成槽—注入泥浆—排渣",{"key":23,"text":24,"correct":18},"D","分段成槽—导墙—吸泥清底—浇筑混凝土","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]