[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1122796,791,1,"单选题","关于提高经济技术指标的相关措施，以下说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","适当的爆破储备量，以满足挖掘机连续作业的要求。",false,{"key":16,"text":17,"correct":18},"B","在保证良好的爆破效果的前提下，尽可能减少基建投资和爆破工程量，加快基建工程的建设进度，降低爆破成本",true,{"key":20,"text":21,"correct":14},"C","在露天开采过程中，爆破破碎效果直接或间接影响各个工序的成本，因而必须有合理的矿岩块度，以提高后续工序的作业效率，使开采总成本最低",{"key":23,"text":24,"correct":14},"D","采场内山头多，凿岩困难时，可以选择一定的标高以上为硐室爆破范围，形成宽阔的工作面，在这种情况下应权衡铲运能力，避免因爆破范围大而积压投资","选项B所描述的内容，是提高经济技术指标的主要要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]