[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1122771,791,1,"单选题","关于矿山地面工程的高程控制网的设立，做法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应保持高程点在施工期间的位置稳定",false,{"key":16,"text":17,"correct":18},"B","地势坡度大时，可拉长两水准点之间的距离以减少测量工作量",true,{"key":20,"text":21,"correct":14},"C","高程控制网可进行两级布设",{"key":23,"text":24,"correct":14},"D","宜在大型建筑物附近测设±0. 000m水准点","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]