[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1122722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1122722,791,1,"单选题","无须列人铺杆质量检验项目内容的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","抗拔力",false,{"key":16,"text":17,"correct":18},"B","树脂与围岩的粘结力",true,{"key":20,"text":21,"correct":14},"C","锚杆杆体材质",{"key":23,"text":24,"correct":14},"D","托盘密贴岩帮","",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]