[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121523":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1121523,790,1,"单选题","专项工程施工技术方案的变更应根据项目条件的变化进行，方案变更，必须由( )进行审批。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理及总监理工程师",false,{"key":16,"text":17,"correct":14},"B","项目主任工程师及总监理工程师",{"key":19,"text":20,"correct":14},"C","施工企业技术负责人及设计",{"key":22,"text":23,"correct":24},"D","施工企业技术负责人及总监理工程师",true,"2021\u002F2020版教材P264页 3.审批流程施工单位技术部门组织本单位施工技术、安全、质量等部门的专业技术人员对编制的专项施工方案进行审核。经审核合格后，由施工单位技术负责人签字，实行施工总承包的，专项方案应当由总承包单位技术负责人及相关专业承包单位技术负责人签字确定。不需专家论证的专项方案，经施工单位审核合格后报监理单位，由项目总监理工程师审核签字。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]