[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121521":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1121521,790,1,"单选题","建筑工程实行施工总承包的，其中深基坑工程施工由专业地基基础公司分包，基坑支护专项施工方案可由( )编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基坑支护设计单位",false,{"key":16,"text":17,"correct":18},"B","地基基础专业公司",true,{"key":20,"text":21,"correct":14},"C","建筑设计单位",{"key":23,"text":24,"correct":14},"D","业主委托其他专业单位","2021\u002F2020版教材P262页 \"建筑工程实行施工总承包的，专项方案应当由施工总承包单位组织编制。其中，起重机械安装拆卸工程、深基坑工程、附着式升降脚手架等专业工程实行分包的，其专项方案可由专业承包单位组织编制。\"",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]