[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1121513,790,1,"单选题","不需要专家论证的专项施工方案，审批流程为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位技术部门组织专业人员审核→施工单位技术负责人签字→总监理工程师审核、签字",true,{"key":16,"text":17,"correct":18},"B","施工单位项目技术负责人组织专业人员审核→施工单位技术负责人签字→总监理工程师审核、签字",false,{"key":20,"text":21,"correct":18},"C","专业承包单位技术负责人组织专业人员审核→专业承包单位技术负责人签字→总监理工程师审核、签字",{"key":23,"text":24,"correct":18},"D","施工单位项目技术负责人组织专业人员审核→施工单位技术负责人签字→业主项目负责人或总监理工程师审核、签字","2021\u002F2020版教材P264页 3、审批流程：施工单位技术部门组织本单位施工技术、安全、质量等部门的专业技术人员对编制的专项施工方案进行审核。经审核合格后，由施工单位技术负责人签字，实行施工总承包的，专项方案应由总承包单位技术负责人及相关专业承包单位技术负责人签字确定。不需要专家论证的专项方案，经施工单位审核合格后报监理单位，由项目总监理工程师审核签字。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]