[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121468":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121468,790,2,"多选题","关于混凝土工程雨期施工的说法，正确的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","对粗、细骨料含水率实时监测，及时调整混凝土配合比",true,{"key":16,"text":17,"correct":14},"B","选用具有防雨水冲刷性能的模板脱模剂",{"key":19,"text":20,"correct":14},"C","雨后应检查地基面的沉降，并应对模板及支架进行检查",{"key":22,"text":23,"correct":24},"D","大雨、暴雨天气不宜进行混凝土露天浇筑。",false,{"key":26,"text":27,"correct":24},"E","梁板同时浇筑时应沿主梁方向浇筑","ABC","2021\u002F2020版教材P128页 五、混凝土工程（4）除采用防护措施外，小雨、中雨天气不宜进行混凝土露天浇筑，且不应开始大面积作业面的混凝土露天浇筑；大雨、暴雨天气不应进行混凝土露天浇筑。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]