[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121461":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1121461,790,1,"单选题","雨期CFG桩施工，槽底预留的保护层厚度最小限值是( )m。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.2",false,{"key":16,"text":17,"correct":14},"B","0.3",{"key":19,"text":20,"correct":21},"C","0.5",true,{"key":23,"text":24,"correct":14},"D","0.7","2021\u002F2020版教材P127页 (5)CFG桩施工，槽底预留的保护层厚度不小于0.5m。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]