[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1121455,790,1,"单选题","冬期施工混凝土搅拌时，当仅加热拌合水不能满足热工计算要求时，可直接加热的混凝土原材料是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水泥",false,{"key":16,"text":17,"correct":14},"B","外加剂",{"key":19,"text":20,"correct":14},"C","矿物掺合料",{"key":22,"text":23,"correct":24},"D","热骨料",true,"2021\u002F2020版教材P123页 （3）冬期施工混凝土搅拌前，原材料的预热应符合下列规定：1）宜加热拌合水。当仅加热拌合水不能满足热工计算要求时，可加热骨料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]