[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121451":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121451,790,2,"多选题","关于混凝土施工期间的测温项目与频次的说法，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","室外气温测量最高、最低气温",true,{"key":16,"text":17,"correct":14},"B","环境温度每昼夜不少于4次",{"key":19,"text":20,"correct":21},"C","搅拌机棚温度每一工作班不少于3次",false,{"key":23,"text":24,"correct":21},"D","外加剂溶液温度每一工作班不少于2次",{"key":26,"text":27,"correct":14},"E","混凝土出机、浇筑、入模温度每一工作班不少于4次","ABE","2021\u002F2020版教材P124页 见表2A312061-3施工期间的测温项目与频次表，冬期施工期间搅拌机棚温度测温频次每一工作班不少于4次；外加剂溶液温度测温频次每一工作班不少于4次。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]