[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1121193,790,1,"单选题","关于模板拆除施工的做法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","跨度8m的钢筋混凝土梁，其强度必须达到设计要求的75%时方可拆除底模",false,{"key":16,"text":17,"correct":14},"B","当设计无要求时，先支的后拆，后支的先拆",{"key":19,"text":20,"correct":14},"C","拆除申请手续需经项目技术负责人批准",{"key":22,"text":23,"correct":24},"D","底模拆除时，标准条件养护试块的抗压强度应符合设计要求",true,"2021\u002F2020版教材P62 当混凝土强度达到设计要求时，方可拆除底模及支架，当设计无具体要 求时，同条件养护试件的混凝土抗压强度应符合表规定。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]