[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121174":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1121174,790,1,"单选题","现浇钢筋混凝土楼盖施工中，梁的跨度为6m，板的跨度为4m，当设计无特别要求时，楼盖拆模时现场混凝土强度应达到设计强度的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50%",false,{"key":16,"text":17,"correct":18},"B","75%",true,{"key":20,"text":21,"correct":14},"C","90%",{"key":23,"text":24,"correct":14},"D","100%","2021\u002F2020版教材P62 表2A312031底模拆除时的混凝土强度要求。针对本题，跨度6m的现浇钢筋混凝土梁，底模拆除时应达到设计强度的75%；",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]