[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1121169,790,1,"单选题","梁、板钢筋绑扎时，板、次梁与主梁交叉处，下列叙述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","板的钢筋在上，次梁的钢筋居中，主梁的钢筋在下；当有圈梁或垫梁时，主梁的钢筋在上",true,{"key":16,"text":17,"correct":18},"B","次梁的钢筋在上，板的钢筋居中，主梁的钢筋在下；当有圈梁或垫梁时，主梁的钢筋在上",false,{"key":20,"text":21,"correct":18},"C","板的钢筋在上，主梁的钢筋居中，次梁的钢筋在下；当有圈梁或垫梁时，主梁的钢筋在下",{"key":23,"text":24,"correct":18},"D","主梁的钢筋在上，次梁的钢筋居中，板的钢筋在下；当有圈梁或垫梁时，主梁的钢筋在下","2021\u002F2020版教材P65 4.梁、板钢筋绑扎（6）板、次梁与主梁交叉处，板的钢筋在上，次梁的钢筋居中，主梁的钢筋在下；当有圈梁或垫梁时，主梁的钢筋在上。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]